Following Fall Fest, we will begin making repairs on Monkey Brook Road. This project involves repairing the failed culvert beneath the sunken area above Riley Road.
Construction equipment will start arriving Friday, October 11, and crews will begin work around 8AM on Monday, October 14. We expect the project to be completed by Wednesday, October 23. During daytime hours, the contractor will manage one-way traffic through the work zone, with two-way traffic anticipated to be open at night.
Please be sure to respect all signage and be patient and courteous while navigating through any work zones.